Planning a mixed container: CBM, carton data and a loading sheet

How to turn carton data into a mixed container plan, with a worked CBM example, a loading sheet template and the packing choices that change usable volume.

This guide is for the buyer who has four or five wooden toy styles ready to ship and needs to know whether they fit one container, where the spare volume sits and what the loading sheet should say. Use it after the carton dimensions are measured and before the deposit, because the carton spec decides both the freight cost and the damage rate. The output is a one-page loading sheet with a volume total, a weight total and a fill ratio against the container you intend to book.

The numbers below are illustrative and rounded. Every figure must be replaced with carton data measured for your own order.

The formula and the usable volume

Container capacity is nominal; the volume you can actually fill is lower because of carton gaps, pallets and how the last row lands at the door.

`` CBM per carton = L × W × H (cm) ÷ 1,000,000 Total CBM = cartons × CBM per carton Usable volume = nominal capacity × fill factor (85–90%) Fill ratio = total CBM ÷ usable volume ``

ContainerNominal capacityUsable at 85–90%Note for wooden toys
20GPabout 28 m³about 23.8–25.2 m³Volume-limited before weight for most toy loads; dense items can hit road weight limits first.
40GPabout 58 m³about 49.3–52.2 m³Good middle option when a 20GP is full and a 40HQ is too large.
40HQabout 68 m³about 57.8–61.2 m³The extra height rewards light, stackable cartons; check the door height for tall cartons.

Two checks sit beside the volume. For LCL, freight is commonly charged on the higher of volume and weight at a ratio of 1 CBM to 1,000 kg, and wooden toys are usually light enough that volume drives the charge. For FCL, confirm the payload limit with the forwarder, because road weight rules in the destination market can bind before the container's rated payload.

Worked example: five styles into a 20GP

An order of five styles, all measured to the nearest centimetre. Cartons are single-SKU and not palletised.

StyleQtyPcs/ctnCartonsCarton cmCBM totalGross kg
A: stacking rings1,200245050 × 40 × 303.000600
B: peg puzzle960244055 × 40 × 252.200420
C: play kitchen12026070 × 45 × 356.615780
D: train set1,800306060 × 40 × 355.040900
E: pull-along duck2,400485045 × 35 × 302.3625450
Total6,480—260—19.21753,150

The arithmetic, row by row:

  1. Cartons per style. Divide the order quantity by pieces per carton and round up. Style A: 1,200 ÷ 24 = 50 cartons.
  2. CBM per carton. Multiply the three dimensions in centimetres and divide by 1,000,000. Style A: 50 × 40 × 30 = 60,000 cm³ = 0.060 m³.
  3. CBM per style. Cartons × CBM per carton. Style A: 50 × 0.060 = 3.000 m³.
  4. Total volume. Add the styles: 3.000 + 2.200 + 6.615 + 5.040 + 2.3625 = 19.2175 m³.
  5. Fill ratio. Against 23.8 m³ usable: 19.2 ÷ 23.8 = 81%. Against 25.2 m³: 76%.
  6. Weight check. 3,150 kg total. Volume is the binding limit here, not weight, but confirm the forwarder's payload limit before booking.

Now apply a measurement margin. Cartons are rarely exactly nominal, and a 1 cm error on each dimension adds roughly 8% to a carton's volume. Repeating the calculation with a 5–8% margin gives about 20.2–20.8 m³, or a fill ratio of 80–87% against the conservative usable figure. That is a workable plan with 3–4.5 m³ left for a late style or a carton-size correction.

On the LCL question: a common rule of thumb is that above roughly 15 m³ it is worth pricing a 20GP against the equivalent LCL space, because the fixed costs of a full container are spread over more volume. Confirm with your forwarder; the crossover moves with the trade lane and the season.

Building the loading sheet

The loading sheet is the document the factory, the inspector and the forwarder all work from. Keep the columns fixed and fill them from measured data, not from the quotation.

LineStyle / SKUQtyCartonsCarton cmTotal CBMGross kgPalletLoad zone
1A: stacking rings1,2005050 × 40 × 303.000600nonose
2B: peg puzzle9604055 × 40 × 252.200420nonose
3C: play kitchen1206070 × 45 × 356.615780nomiddle
4D: train set1,8006060 × 40 × 355.040900nomiddle
5E: pull-along duck2,4005045 × 35 × 302.3625450nodoor
Total—6,480260—19.21753,150——

Add a footer to the sheet with four numbers: total CBM, total gross weight, the usable volume of the booked container and the resulting fill ratio. A fifth line carries the contingency: total CBM × 1.05, so a late addition or a corrected carton does not turn into a second booking.

Three loading rules go on the same sheet. Put dense cartons at the nose and low, keep crushable or light cartons at the door, and count cartons at the container in front of the inspector rather than after departure. The seal number and the container condition belong on the sheet too, with photographs.

Packing choices that change usable CBM

What goes wrong most often

A short email gets the data in the right form:

``` Subject: Carton data for loading sheet — <model list>

For each SKU, please send:

  1. Pieces per carton
  2. Carton dimensions L × W × H in cm, measured from a production carton
  3. Gross weight per carton in kg
  4. Inner packing: polybag, divider or inner box
  5. Pallet pattern and cartons per pallet, if palletised
  6. Date the first carton will be available for measurement

Please confirm whether the dimensions are measured or estimated. ```

Timing the consolidation

  1. Freeze carton data first. Get measured dimensions, gross weight and pieces per carton for every style before you approve the deposit. This is the input everything else depends on.
  2. Set production dates per style. A mixed container is only as early as its slowest style. Put the style with the longest lead time first in the plan.
  3. Book inspection 2–3 weeks ahead in August to November, and agree that inspection happens after packing and before loading.
  4. Confirm the consolidation date with the forwarder, then work backwards to the latest factory delivery date for each style. Add a buffer of several days, not hours.
  5. Plan around the calendar. Chinese New Year shuts production for roughly 3–5 weeks around late January or February, and freight bookings tighten 4–6 weeks before it. The August–November peak commonly adds 2–3 weeks to production.
  6. Reconcile at loading. Carton count, seal number, container condition and photographs go onto the loading sheet before the doors close.

How to use this with a supplier

The method behind combining styles is on the mixed containers page; the volume check can be run quickly with the container load calculator. Carton design is also a price line, which the price structure guide covers. When the loading sheet is ready, send it with the quote request so the freight and production dates are quoted against the same plan.

Matching stage: supplier evaluation. When the specification is fixed, request a quote.